Dovetail Developments is honoured to announce that we have received a Commendation award from Knox City Council for our Charlotte’s Mews project in the Design and Development Excellence Awards for 2019. This beautiful collection of contemporary townhouses qualified under Knox City Council’s “Local Living” category and has been celebrated for its contemporary expression of dwelling design and clever site planning model. Dovetail will continue to revitalise local communities through championing modern and innovative building design, and look forward to bringing the sophistication of Dovetail’s signature look, as captured by Charlotte’s Mews, to the Bayside area. Click here for more information.

Publish Date: 29 March 2018

Dovetail Developments is honoured to announce that we have received a Commendation award from Knox City Council for our Charlotte’s Mews project in the Design and Development Excellence Awards for 2019. This beautiful collection of contemporary townhouses qualified under Knox City Council’s “Local Living” category and has been celebrated for its contemporary expression of dwelling design and clever site planning model. Dovetail will continue to revitalise local communities through championing modern and innovative building design, and look forward to bringing the sophistication of Dovetail’s signature look, as captured by Charlotte’s Mews, to the Bayside area. Click here for more information.

Publish Date: 27 March 2018

Works are progressing well on-site. It’s fantastic to see external finishes being applied to facades. The design vision for this project is really starting to reveal itself!

Publish Date: 31 Jan 2018

After a couple of set-backs were experienced earlier this month at Charlotte’s Mews, works are continuing at Adele Avenue. Internal fit out is underway and NBN is being installed. We look forward for the bulk of the townhouses reaching completion over the next 4-6 weeks.

Publish Date: 22 Dec 2017

Great progress has been made on-site with this project, particularly in regards to external finishes. The application of rear units’ external cladding is almost complete whilst the front units have had their ground floor brickwork finalised and first floor prepared for cladding.

Publish Date: 15 Nov 2017

Great progress has been made on-site with this project, particularly in regards to external finishes. The application of rear units’ external cladding is almost complete whilst the front units have had their ground floor brickwork finalised and first floor prepared for cladding.

Publish Date: 9 Oct 2017

This project is coming along nicely with roofing nearly complete and window installation in progress. Service rough in works are also well-underway, great to see.

Publish Date: 28 Aug 2017

Framing has been completed for most units on site. The brickwork on rear units has also commenced. This project is really starting to take shape!

Publish Date: 28 July 2017

The steelwork for this project is complete with timber framing continuing to go up on site. The rough in works, particularly for NBN services, have also begun on site. This project is really starting to come together!

Publish Date: 30 June 2017

We’ve had a bumper few weeks out at Charlotte’s Mews! All slabs are now poured, steelwork is underway and the first floor timber framing is being installed in the rear townhouses. It’s all full steam ahead at Charlotte’s Mews!

Publish Date: 31  May 2017

Slabs are going down! Some very exciting news for this project!

Publish Date: 3  May 2017

Preparations are taking place on site for the slab to be poured next week! We are very excited to this project advancing!